Critical Path of a Project With Multiple Starts & Finishing Activities
Engineer4Free Engineer4Free
224K subscribers
6,792 views
134

 Published On Feb 12, 2024

This tutorial shows how to draw the network diagram and find the critical path of a project when there are multiple finishing/final activities. In this scenario, each starting activity must have an ES of 0, and you must use the latest EF of all finishing activities as the LF of all finishing activities. This video is part of a full free course on project management.