Reconstruction Update: Week 8 Progress Report.
Southport Golf Club Southport Golf Club
320 subscribers
428 views
7

 Published On Oct 29, 2023

In this week’s update, our Course Superintendent, Stuart Moore, provides a detailed account of the progress made during the eighth week of the reconstruction process.
The video covers the latest developments on both the first and fourth holes. On the first hole, the retaining wall near the 1st Tee has been completed and the tee shaped, the area to the left of the first tee box is being prepared to be turned into car parking spaces.

On the fourth hole, the drainage has been installed and gravel added. Next it will be time for the sand layer (growing media).

There are a few things you can do to help with the project:
1. Stay safe by following the signs and staying out of the work areas.
2. Read the signage and keep informed about the project.
3. Be patient and understanding as the project progresses.
We appreciate your cooperation and understanding during this time. We are committed to making the Southport Golf Club the best it can be for our members and guests.

Don't forget to hit that thumbs up and subscribe to stay up to follow this reconstruction journey with us!